Prendos was engaged to assist Southern Cross Hospitals in resolving weathertightness issues at Brightside Hospital – a modern, private surgical hospital located in central Auckland.


Client: Southern Cross Hospitals
Location: Brightside Hospital, Auckland
Services Provided: Weathertightness Remediation


The Job

Prendos was engaged to assist Southern Cross Hospitals in resolving weathertightness issues at Brightside Hospital – a modern, private surgical hospital located in central Auckland.

Our Solution

Our multi-disciplinary team investigated the issues, recommended repairs, designed a solution and administered the remediation works. We also assisted Southern Cross in resolving issues with the building’s original design and build contractor.

The most challenging aspect of the job was coordinating and undertaking significant reconstruction works around a functioning surgical hospital. Issues such as construction noise, patient privacy, health and safety requirements and programme flexibility all had to be considered and managed.

The Outcome